edited.jpg

featured projects

 

Gadsden Power Station

Gadsden, AL

This project involved the environmental abatement of a former 200-megawatt (MW) power generation facility located in Gadsden, Alabama. The plant, owned by Southern Energy, comprised two 100 MW boiler units (Units #1 and #2), both of which were retired in 2020. Historically, the facility operated seasonally—averaging four months per year—with peak operation occurring during the summer months to support the regional electric grid. The overall site footprint encompasses approximately 50 acres and includes:

  • Powerhouse with boilers, turbines, and generators

  • Emission stacks

  • Electrical transformers

  • Warehousing and storage buildings

  • Aboveground storage tanks (ASTs)

  • Associated ancillary systems and infrastructure

EACI performed comprehensive asbestos abatement and hazardous materials remediation throughout the site. This included high-risk materials within boiler systems, turbine halls, piping, and electrical systems. All abatement activities were executed under a compressed four-month schedule, with strict adherence to applicable OSHA, EPA, and state environmental regulations.

oWNER: Alabama power

contract amount: $2,530,000

start date: october 2023

Completion date: february 2024



 

Nutrien Plant

White Springs, FL

EACI was contracted to perform the abatement of approximately 200 square feet of transite (asbestos-containing) material from various structures located at the project site in White Springs, Florida. The transite materials were located at elevated heights across multiple buildings, requiring the use of high-reach aerial lifts for safe and efficient access.

Execution Approach:
Due to the nature of the work and the configuration of the structures, the project presented significant safety challenges. In response, EACI’s safety team developed and implemented site-specific procedures to address elevated work risks, regulatory compliance, and exposure control.

All work was performed in accordance with OSHA 29 CFR 1926.1101 and applicable state and local environmental regulations, with a strong emphasis on containment, air monitoring, and worker protection.

Owner: Nutrien

Contract Amount: $704,000.00

Start Date: July 2023

Completion Date: February 2024



 

McKee Run Generating Station

Dover, de

Environmental Assurance Company, Inc. (EACI) was contracted to perform comprehensive asbestos abatement at the McKee Run Power Plant in Dover, Delaware—a decommissioned 136-megawatt (MW) facility owned by the City of Dover. The site included two retired 17 MW boiler units (Units #1 and #2) and one 102 MW boiler unit (Unit #3), previously fueled by natural gas with No. 2 fuel oil as a backup.

Historically, the plant operated seasonally—primarily during summer months—and supported the regional electric grid. Following full retirement of the facility, EACI was tasked with the safe and regulatory-compliant removal of asbestos-containing materials (ACMs) throughout the site. EACI’s work involved abatement of ACMs from the following structures and components:

  • Powerhouse boilers, turbines, and generators

  • Transformer yards and electrical rooms

  • Control rooms, maintenance shops, and administrative offices

  • Boiler rooms, turbine decks, piping systems, and ductwork

  • Fuel handling and transfer areas

  • Aboveground storage tanks (ASTs) and associated infrastructure

  • Two large asbestos-clad cooling towers on the north side of the plant:

    • Cooling Tower 1: 155' x 53'

    • Cooling Tower 2: 180' x 54'

Each cooling tower was constructed of pressure-treated wood, fiberglass, plastic fill trays, and rubber-coated wire hangers mounted on concrete foundations. Asbestos-containing materials were identified in siding panels, piping insulation (fiberglass and metal), and black asbestos mastic coatings. Due to the complex and deteriorated condition of many structural components, EACI developed a site-specific work plan addressing elevated work, confined space protocols, and phased decontamination strategies. The project was performed in compliance with:

  • OSHA 29 CFR 1926.1101 (Asbestos)

  • EPA NESHAP Standards

  • Applicable Delaware Department of Natural Resources & Environmental Control (DNREC) requirements

EACI utilized a combination of negative pressure enclosures, HEPA filtration, and controlled wet methods to ensure safe fiber containment and environmental protection throughout the project.

Owner: city of dover

contract amount: $3,443,306.00

start date: january 2024

completion date: may 2024



 

Dayton Power & Light – Aberdeen Generating Station

Aberdeen, oh

Following the catastrophic explosion of the Unit #1 Boiler, EACI was engaged by Dayton Power & Light to perform emergency response, cleanup, and asbestos abatement services. The explosion resulted in widespread contamination of building components and mechanical systems with asbestos-containing materials (ACM).

Project Execution:
EACI mobilized immediately and maintained an average daily workforce of approximately 90 trained personnel. Work was conducted on a 12-hour shift schedule, six days per week. The scope included the removal, decontamination, and compliant disposal of asbestos-contaminated debris under full containment, adhering to all applicable OSHA, EPA, and state regulatory standards.

Safety Performance:
Over the course of the project, EACI logged more than 200,000 man-hours without a single recordable incident, lost-time injury, or OSHA violation. Rigorous safety protocols, continuous oversight, and a robust site-specific health and safety plan were critical to this outcome, especially given the hazardous and high-pressure conditions of emergency response work.

Owner: dAYTON pOWER & LIGHT (Now aes ohio)

CONTRACT AMOUNT: $7,800,000.00

START DATE: January 2017

completion date: august 2017



 

Purdue Memorial Union Club Hotel Renovation

West lafayette, in

EACI was contracted to perform interior selective demolition and mold remediation services as part of a large-scale renovation of the historic 180-room Memorial Union Club Hotel. The scope included the remediation of microbial growth and the demolition of guest room bathrooms, wall coverings, ceilings, and flooring across all affected units.

Execution Approach:
Work was executed under controlled conditions with strict adherence to industry standards for mold remediation, including containment, negative air pressure, and HEPA-filtered air scrubbing. Demolition activities were coordinated to support the renovation schedule and minimize disruption within the operational facility.

Manpower & Safety:
EACI maintained an average on-site workforce of 50 trained personnel throughout the duration of the project. The work was completed without any recordable safety incidents or lost-time accidents, reflecting EACI’s commitment to safety and compliance on occupied and sensitive sites.

owner: purdue university

CONTRACT AMOUNT: $600,000.00

START DATE: August 2019

Completion date: december 2019



 

Duke Energy Wabash River Generating Station

TERRE HAUTE, IN

EACI was contracted to perform comprehensive asbestos and hazardous materials abatement at the retired Wabash Generating Station in preparation for facility demolition. The scope encompassed the removal of regulated materials from all six generating units, including:

  • Boilers

  • Turbines

  • Induced Draft (ID) Fans

  • Dust Collectors

  • Back Pass Assemblies

  • Full facility-wide pipe insulation

All work was conducted in compliance with federal, state, and local environmental and safety regulations, including OSHA 29 CFR 1926.1101 and EPA NESHAP guidelines.

Execution & Safety Performance:
EACI executed over 400,000 man-hours on-site without any recordable safety incidents or lost-time injuries. The team actively participated in Duke Energy’s Behavioral-Based Safety (BBS) program, reinforcing a proactive safety culture and hazard mitigation framework throughout the project lifecycle

owner: duke energy

contract amount: $11,800,000.00

Start date: SEPTEMBER 2017

COMPLETION DATE: MARCH 2019



 

Port Authority Ashtabula Power Plant

Ashtabula county, oh

As part of a larger infrastructure redevelopment initiative aimed at upgrading water import capacity to support local businesses, residents, and surrounding counties in Ashtabula, the former FirstEnergy Power Plant underwent extensive environmental remediation. Environmental Assurance Company, Inc. served as the prime environmental contractor for the project.

Scope of Work:
EACI was subcontracted to perform asbestos abatement services within four (4) six-story utility boilers. The scope included the identification, containment, removal, and lawful disposal of all asbestos-containing materials (ACM) associated with boiler insulation, refractory materials, and ancillary piping systems. All work was conducted in accordance with applicable OSHA, EPA, and state regulations, including OSHA 29 CFR 1926.1101 and EPA NESHAP standards.

Performance & Execution:
EACI delivered its scope on a compressed, time-sensitive schedule without compromising safety or quality. All work was completed professionally, without incident, and in alignment with aggressive project milestones set by the client and regulatory stakeholders.

owner: ashtabula port authority

Contract amount: $609,000.00

Start date: december 2016

Completion date: march 2017



 

Indianapolis Power & Light Monument Circle

Indianapolis, in

The IPL Monumental Makeover Project involved the renovation of the IPL Electric Building to serve as the new headquarters for the Unified Shared Services Business Unit (USSBU). The redevelopment supported the creation of approximately 100 new jobs and aimed to establish a modern, cohesive workplace aligned with IPL’s corporate identity and community presence.

Scope of Work:
EACI was contracted to perform complete asbestos abatement throughout the facility in compliance with all applicable OSHA and EPA regulations. Additionally, EACI executed comprehensive interior demolition services, including the removal of:

  • Masonry walls

  • Interior and exterior windows

  • Doors and entry systems

  • Drywall and interior partitions

  • Flooring and subfloor systems

  • HVAC components

  • Mechanical, Electrical, and Plumbing (MEP) systems

Project Highlights:
EACI’s work was critical to enabling subsequent renovations and was performed on schedule and in coordination with multiple trades under a fast-track delivery model. All work was executed with a strong focus on safety, regulatory compliance, and minimal disruption to adjacent occupied spaces.

OWNER: Indianapolis power & light (Now aes indiana)

CONTRACT AMOUNT: $3,400,000.00

START DATE: SEPTEMBER 2015

COMPLETION DATE: JULY 2016



 

Indianapolis Motor Speedway

indianapolis, in

As part of a major renovation to the historic Indianapolis Motor Speedway—originally constructed in 1909—EACI was contracted to perform environmental remediation services in preparation for structural upgrades. The renovation supported significant infrastructure improvements to key spectator areas, including the Paddock, Stand A, and Stand B.

Scope of Work:
EACI’s primary scope involved the removal of lead-based paint (LBP) from existing structural steel columns to allow for the safe installation of new structural steel and roofing systems. All abatement activities were conducted in accordance with OSHA 29 CFR 1926.62 and EPA RRP regulations for lead safety and containment.

Associated Renovation Highlights (by others):

  • Removal and replacement of roofing systems along the front straightaway of the Paddock, Stand A, and Stand B

  • Installation of approximately 13,000 new spectator seats

  • Removal of over 500,000 SF of legacy catch fencing

  • Installation of new, modern mesh catch fencing

Performance & Safety:
EACI completed its scope on time and without any recordable safety incidents or lost work time, demonstrating strict adherence to safety protocols and environmental compliance on a high-profile, fast-paced project.

Owner: Indianapolis Motor Speedway, LLC

Contract Amount: $989,000.00

Start Date: August 2015

Completion Date: January 2016



 

Birch Bayh Federal Courthouse

INDIANAPOLIS, IN

The Birch Bayh Federal Courthouse renovation was a multi-phase; three-year project performed while the facility remained fully occupied. The project involved extensive infrastructure upgrades and modernization efforts within a historically significant and federally protected building.

Scope of Work:
EACI’s scope included:

  • Asbestos abatement in mechanical chases, ductwork, and building finishes

  • Lead-based paint abatement from structural elements and decorative surfaces

  • Selective demolition to support upgrades to HVAC systems, including access to confined spaces and utility shafts

Execution Strategy:
All work was performed under strict security protocols and in compliance with federal regulations. EACI was operating in sensitive, high-security zones without interrupting the daily operations of key tenants including the U.S. Bankruptcy Court, Federal Judges’ chambers, U.S. Marshals Service, and various other federal agencies.

Special Considerations:

  • Preservation of historic architectural features

  • Work scheduling and containment to prevent disruption to court proceedings and federal operations

  • Close coordination with federal security personnel and GSA representatives

Owner: General Service Administration

Contract Amount: $6,200,000.00

Start Date: July 2009

Completion Date: August 2012



 

Indianapolis Power & Light - Harding Street Station

indianapolis, in

EACI was contracted to perform asbestos abatement services as part of the Unit 7 boiler overhaul at the IPL Harding Street Station. The project required the removal of asbestos-containing insulation and associated lagging materials from various high-temperature systems and components throughout the unit.

Scope of Work:

  • Complete removal of ACM insulation and lagging from:

    • Unit 7 Boiler

    • Hoppers and ducts

    • Cooling towers

    • FGD (Flue Gas Desulfurization) systems

    • Piping systems

    • Dust collectors

Execution & Compliance:
All work was performed under full containment conditions in accordance with OSHA 29 CFR 1926.1101 and EPA NESHAP standards. EACI implemented comprehensive safety and environmental controls to ensure proper handling, air monitoring, and disposal of regulated materials during the four-month outage period.

owner: INDIANAPOLIS POWER & LIGHT (Now aes indiana)

CONTRACT AMOUNT: $1,450,00.00

START DATE: OCTOBER 2010

COMPLETION DATE: DECEMBER 2010



 

Indiana State House

indianapolis, in

The Indiana Statehouse renovation was a multi-year, phased modernization effort conducted while the building remained fully operational. The project involved critical infrastructure upgrades while preserving the historic and architectural integrity of the facility.

Scope of Work:
EACI was contracted to perform:

  • Asbestos abatement in mechanical systems and building materials

  • Lead-based paint remediation from structural and decorative surfaces

  • Selective demolition to facilitate the phased replacement and upgrade of HVAC systems

Execution Strategy:
All work was executed in historically significant areas under heightened security protocols. EACI coordinated closely with state officials to ensure zero disruption to the daily operations of the Governor’s Office, State Senate, House of Representatives, and other governmental functions housed within the Statehouse.

Key Considerations:

  • Preservation of historic finishes and architectural elements

  • Adherence to state and federal environmental and safety regulations

  • Strategic phasing and containment to minimize occupant impact

owner: state of indiana

contract amount: $1,950,000.00

start date: May 2006

completion date: december 2009